Leadge.com首页 > 知识库
文章搜索
管理的挑战——软技能在项目管理中的应用案例
2006-7-3 18:03:11  作者:赵克琛
  
The overall plan tied customer payment to milestones, as firm, fixed-price contracts require. “I don’t think we had a choice,” Gowans says. “That’s the only way the customer is assured that, when the dollars are paid, progress is made. But you must pick increments that are achievable.”

The setup provides management challenges, especially when managing the critical path proactively, Abramovici says. “On one hand, payment milestones are good because they allow a continuous focus on those deliverables and permit the customer to see progress being made,” Abramovici says. “But if there are too many milestones too closely spaced, it takes away flexibility as the program progresses. You can’t use a rolling-wave approach because the milestones are locked down based on payment.”

The original (baseline) cost and schedule was amended through the life of the project by incorporating customer-mandated and approved changes of scope proposals, which consequently modified the project cost and acceptance review date.

Progress Report

Engineering work paralleled the SPDM product design effort. The engineering team and management scrutinized any changes requested by the customer to ensure the existing design would meet the new demands and to define whether or not the new requirements were within the original scope. The team immediately discussed out-of-scope changes with the customer and, if the customer approved implementation, the team analyzed these requests to identify technical, cost, schedule, human resources, facilities and risk impacts.

此文章共有17页  上一页 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 下一页

文章来源:中国项目管理资源网

发表评论    【推荐】 【打印
我来评两句 查看最新评论〗 
请您注意:
·遵守中华人民共和国的各项有关法律法规
·承担一切因您的行为而导致的法律责任
·本网留言板管理人员有权删除其管辖留言内容
·您在本网的留言,本网有权在网站内转载或引用
·参与本留言即表明您已经阅读并接受上述条款
昵称: 匿名
 
图片广告
热点文章
论坛精贴