初学Project,请问如何做这个题。谢谢。

2008/9/11 15:09:09 |  2567次阅读 |  来源:原创   【已有0条评论】发表评论

Exercise #5 on page 106 of the text provides a list of tasks and
dependencies for building a new system.(I have provided the list at the bottom:))

3. Let us assume that we have three such systems to build (inventory, order entry, and customer support) – each during one iteration of an agile development methodology. Further assume that the project will be completed during normal working days (Monday to Friday, 30 hours per week, no work on statutory holidays). Further assume that the project will start September 2nd, 2008. Statutory holidays include Thanksgiving (Oct13, Christmas (Dec 25), Boxing Day (Dec 26) and New Year’s Day (Jan 1).

4. Build a Project model for this, remembering to add a final “Party”milestone after the third iteration.

5. Build a one-page word processed report which incorporates two
embedded images – a network view of a single iteration, and a Gantt chart view of the entire project. These images will have to be scaled to fit the page. There should be a summary sentence at the beginning, outlining the duration of each iteration, as well as the anticipated project completion date.

Task List:

Task ID Description Duration (days) Predessor
0 Start 0 -
1 Meet with user 2 0
2 Review existing forms 1 0
3 Identify and specify 3 1,2
fields
4 Build initial prototype 2 3
5 Develop test data 4 3
(valid data)
6 Develop error test 2 5
data
7 Test prototype 3 4,6
8 Make final refinements 3 7



我刚学project,尝试做了点。感觉很不对。 图片我发不上来。

请大家帮帮忙看看。。。。是不是很简单,然后我想太多了???谢谢哒~~

【 发表评论 0条 】


网友评论
网友评论(共0 条评论)..

请您注意·自觉遵守:爱国、守法、自律、真实、文明的原则
·尊重网上道德,遵守《全国人大常委会关于维护互联网安全的决定》及中华人民共和国其他各项有关法律法规
·严禁发表危害国家安全,破坏民族团结、国家宗教政策和社会稳定,含侮辱、诽谤、教唆、淫秽等内容的作品
·承担一切因您的行为而直接或间接导致的民事或刑事法律责任
·您在中国项目管理资源网新闻评论发表的作品,中国项目管理资源网有权在网站内保留、转载、引用或者删除
·参与本评论即表明您已经阅读并接受上述条款