2008-12-22 10:09:20  作者:佚名
  
Rule #46: Remember, it is often easier to do foolish paperwork that to fight the need for it. Fight only if it is a global issue which will save much future work.

Contractors and Contracting

Rule #47: A project manager is not the monitor of the contractor’s work but is to be the driver. In award fee situations, the government personnel should be making every effort possible to make sure the contractor gets a high score (i.e., be on schedule and produce good work). Contractors don’t fail, NASA does and that is why one must be proactive in support. This is also why a low score damages the government project manager as much as the contractor’s manager because it means that he is not getting the job done.

Rule #48: Award fee is a good tool that puts discipline both on the contractor and the government. The score given represents the status of the project as well as the management skills of both parties. The project management measurement system (PMS) should be used to verify the scores. Consistent poor scores require senior management intervention to determine the reason. Consistent good scores which are consistent with PMS reflect a well-run project, but if these scores are not consistent with the PMS, senior management must take action to find out why.

此文章共有23页  上一页 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 下一页

文章来源:中国项目管理资源网

发表评论    【推荐】 【打印
我来评两句 查看最新评论〗 
请您注意:
·遵守中华人民共和国的各项有关法律法规
·承担一切因您的行为而导致的法律责任
·本网留言板管理人员有权删除其管辖留言内容
·您在本网的留言,本网有权在网站内转载或引用
·参与本留言即表明您已经阅读并接受上述条款
昵称: 匿名
 
图片广告
热点文章
论坛精贴